NEXTDC upgrades FY27 guidance as Scroggie takes responsibility for M3 delay

November 20, 2026 at 8:32 AM GMT+8

NEXTDC has raised its FY27 revenue and earnings guidance after reporting stronger sales growth outside its delayed M3 Melbourne development, while CEO Craig Scroggie has acknowledged the company’s responsibility for the project’s power and community engagement problems.

The data centre operator on 20 November upgraded its FY27 net revenue guidance to AU$485 million-AU$500m, from AU$475m-AU$500m, and underlying EBITDA guidance to AU$260m-AU$275m, from AU$245m-AU$265m.

The revised forecasts remain below the original guidance issued in August, which included revenue and earnings from customer contracts at M3. Those contracts, representing approximately AU$140m each in net revenue and underlying EBITDA in the original forecast, remain excluded while NEXTDC assesses when the affected capacity can be delivered and its financial contribution reliably estimated.

The exclusion also covers M3 capacity that is already billing. NEXTDC said any service level credits payable on those contracts could reduce underlying EBITDA below the new range.

The company said the revenue upgrade reflected stronger sales and growth outside the affected M3 contracts, together with greater confidence in the timing of customer delivery. The higher EBITDA forecast mainly reflects savings from focusing operating expenditure on delivering capacity to customers, together with higher expected net revenue.

NEXTDC reaffirmed its FY27 capital expenditure guidance of AU$4.5bn-AU$5bn, unchanged from 21 October, following a review of its investment programme. The range is AU$750m, or 13-14 percent, below the original August guidance of AU$5.25bn-AU$5.75bn. Excluding about AU$230m of capitalised interest, which the August figure did not include, the reduction is around AU$980m, or 17-19 percent, on a like-for-like basis.

Hard year

Addressing shareholders at the company’s annual general meeting, Scroggie described it as the hardest of his 15 AGMs as CEO and accepted responsibility for the delays at M3.
“As CEO, I am accountable for delivery. Power, planning approvals, construction and community support are all part of delivery. We rely on partners for each of them, and they have their own responsibilities. That does not change mine,” he said.

“At M3 we needed to work more closely with our power and construction partners, and with the community. We are now doing that.”

The M3 expansion in West Footscray has been delayed by problems securing additional grid supply. The additional power requires electricity distributor Jemena to install new power lines, but residents raised concerns about the size of proposed power poles. Jemena subsequently suspended the works, citing safety concerns and a lack of access to work sites resulting from community opposition.

Scroggie said Jemena had recognised that its community engagement and consultation around the network upgrades had been insufficient and was strengthening its approach.

“Those concerns deserved to be heard earlier,” he said. “None of that changes where accountability sits. The upgrade serves our project and our customer. Delivering that project is our job, and I am accountable for it.”

New options

NEXTDC and Jemena are now pursuing several options in parallel to bring power to M3, including alternative routes through industrial streets or underground, alternative substations, upgrades to existing feeders and broader grid options.

Jemena will lead any community consultation and approvals process once its technical solution has been finalised, with NEXTDC saying it will support the process. Scroggie said the company would provide a further update at its half-year results in February, or earlier if there was material progress.

Construction is continuing on the approved development of contracted capacity at M3, and the affected customer contracts remain in place, subject to the customer’s rights. However, the previously announced delay relates to the timing of the next increase in power supply to M3.

Community committee

The company is also changing its approach to community engagement. It is establishing a Community Consultative Committee at M3 and developing a formal engagement plan for the site, and has launched dedicated contact channels and introduced defined response times for complaints and enquiries. NEXTDC plans to develop community engagement plans for all its sites in Australia and Asia.

“We build on industrial land, close to power, network connectivity and our customers,” Scroggie said. “In the past we relied on formal council and state planning processes to set the standard and own the conversation with the community. That is no longer enough.”

“We will now engage earlier and directly, alongside our power and construction partners,” he said.

The capital expenditure review has reinforced a shift away from discretionary development towards completing contracted projects. NEXTDC said most of its FY27 capital spending will be directed towards existing customer commitments at S4 Sydney, M2 and M3 Melbourne, and KL1 Kuala Lumpur.

Uncontracted developments, including M4, M5, S5, S7, GC1 and AK1, as well as new land acquisitions, remain on hold. Future investment will be considered on a project-by-project basis, with NEXTDC requiring customer contracts, returns above its cost of capital, sufficiently advanced power and planning arrangements, and funding in place.

S4 update

The company’s largest contracted development is S4 in western Sydney, which has 250MW of its planned 365MW IT load contracted. Construction is under way on the first 115MW phase, which is expected to begin billing in FY28. Phase 2 remains in the NSW planning process.

NEXTDC said it had a forward order book of 565MW on a pro forma basis at 30 June 2026, including the affected M3 contracts. Scroggie said demand for high-quality, secure and reliable data centre capacity was the strongest he had seen during his time as CEO, with cloud computing and AI continuing to drive demand.

“Demand is not our constraint. Delivery is,” he told shareholders.

The company also said it had sufficient funding to deliver its existing contracted customer capacity and did not expect to raise capital from shareholders for that work at this time. It is continuing to explore capital recycling options, including a potential joint venture structure for S4.

The company said it would prioritise converting contracted capacity into revenue and operating cash flow, rather than committing capital to uncontracted projects. “The rest of the business is performing. FY26 was a record year,” Scroggie said.

NEXTDC operates 18 data centres across Australia and Malaysia and has five sites in development. Its development pipeline exceeds 5GW across Australia and international markets, although uncontracted development projects are currently on hold while the company focuses on delivering its forward order book.

“Outside M3, the business is performing, and demand is the strongest I have seen. Our job is to deliver the value in this business for our shareholders,” he concluded.