IREN details 900MW Wagga campus, but Transgrid capacity not yet secured

Source: IREN, ARCH.
November 23, 2026 at 6:26 AM GMT+8

Australian AI infrastructure company IREN has detailed plans for a proposed 900MW data centre campus near Wagga Wagga in regional New South Wales, including a new high-voltage connection to Transgrid’s local substation, although the availability and allocation of transmission capacity for the project remain subject to the connection process.

The company’s Redbank Data Centre proposal involves up to 900MW of gross electrical capacity, supporting approximately 600MW of IT load. The site, in the rural locality of Rowan south-east of Wagga Wagga and adjacent to the Gregadoo Waste Management Centre, is about 2.5km from Transgrid’s existing 330kV substation.

A scoping report prepared for IREN subsidiary TAS 1 Holdings proposes three new 330kV feeder bays at the Wagga Wagga substation and three underground 330kV cable circuits running generally along the Boiling Down Road corridor to a new on-site 330/132kV bulk power substation.

The proposed on-site substation would include four 375MVA transformers, with four additional 132/33kV primary substations distributing electricity to the five physical data halls. IREN says it will fund the dedicated connection assets and works required as a consequence of the development. However, the final connection design and any wider network augmentation requirements will be determined through ongoing engagement with Transgrid and the formal connection process.

Connection talks

The scoping report says connection planning with Transgrid has been under way since May 2026 on the basis of a proposed 900MW connection, with network studies and substation planning progressing. Transgrid has separately said that indicative capacity in regional NSW, including Wagga Wagga, may provide opportunities for data centres to connect to its transmission network.

In response to a W.Media enquiry about Redbank, Transgrid said it could not disclose information about individual customer connection enquiries or applications because of confidentiality requirements under the National Electricity Rules. It referred to Figure 1.6 of its 2026 Transmission Annual Planning Report, which identifies indicative capacity in regional NSW, including Wagga Wagga, and said opportunities would depend on the requirements and scope of individual connection applications.

Transgrid also referred to its Network Capacity Allocation Policy, which states that transmission capacity is provisionally allocated to a specific large-load project when a Network Connection Agreement (NCA) is signed, and becomes final only if the project meets readiness criteria within three months.

Conditional agreements require proponents to demonstrate meaningful progress against readiness criteria covering permits, construction contracts, land, long-lead equipment and financing. They must also have submitted a complete connection application accepted by Transgrid for review.

Transgrid’s response didn’t establish whether IREN has reached that stage of the process. The scoping report confirms ongoing engagement, but does not identify a signed NCA or a formal allocation of transmission capacity. IREN previously said Redbank was not included in its announced 5GW secured-power portfolio and that it was working towards a grid connection.

The distinction between the proposed 900MW connection and the facility’s expected operating demand is also important. The 900MW figure represents the maximum instantaneous gross electrical capacity required by the development, and not necessarily its expected average consumption.

The report estimates that at full IT load, and using a design annualised power usage effectiveness (PUE) of approximately 1.3, average total facility demand would be around 780MW. Actual consumption would depend on the IT capacity deployed and operating conditions.

Multi-stage delivery

IREN proposes to deliver the campus in stages over approximately six to eight years, with an initial 75MW gross block targeted for 2029 and subsequent blocks of approximately the same size at six-month intervals. The report’s indicative staging reaches the full 900MW by 2035. The project is proposed to be assessed as a single State Significant Development, with construction and grid connection delivered progressively within that approval.

The development would comprise five physical data halls, supporting electrical and telecoms infrastructure, closed-loop cooling systems and a construction workers’ accommodation camp. The indicative design also includes approximately 444 standby diesel generators to provide backup during grid outages and support commissioning, testing and maintenance. IREN says the generators would not be used for continuous electricity generation.

The proposed cooling system uses direct-to-chip technology, circulating coolant through cold plates attached to computing hardware. Heat would be transferred through cooling distribution units and heat exchangers before being rejected through dry coolers and/or chillers.

The scoping report says operational cooling make-up water is expected to be approximately 1 per cent of the total closed-loop system volume annually, although the final system volume and corresponding annual water demand have yet to be determined. The environmental assessment will also examine water supply options, including recycled water, and the capacity of local infrastructure.

Preparing SEARs

The project is at an early stage of the NSW planning process. The proposal includes an amendment to the Wagga Wagga Local Environmental Plan to permit the data centre and associated temporary workers’ accommodation on the site, which is currently rural land. The NSW Planning Portal lists Redbank as a State Significant Development and shows its current status as preparation of Secretary’s Environmental Assessment Requirements, ahead of preparation of the detailed environmental impact assessment.

IREN’s scoping report identifies an expected construction workforce of up to approximately 1,100 people and more than 200 full-time equivalent operational positions at full capacity. Operational staffing is expected to begin at around 50 FTE when the first data block is energised.

The Redbank proposal is separate from IREN’s planned 800MW Bundey data centre development in South Australia. The company has previously announced a transmission connection agreement for Bundey.

The proposed campus is also close to CDC Data Centres’ separately planned development at Gregadoo, which could add up to 1.4GW of data centre capacity in the Wagga Wagga area. Together, the two proposals represent a potential 2.3GW of new data centre demand in the region, although both remain subject to planning and electricity connection processes.