Australian-based global data centre developer Goodman’s plans for an indicative 2,150 apartments in Macquarie Park in Sydney New South Wales have been declared State Significant Development, advancing a major residential proposal close to the company’s approved Project Apollo data centre. The residential development, proposed for 3–5 Talavera Road, comprises five towers ranging from 45 to 60 storeys. The proposal includes a commitment to provide 4% affordable housing in perpetuity.
The residential proposal was formally declared State Significant Development on 27 October, following a recommendation by the Housing Delivery Authority. The declaration allows the project to proceed through the SSD assessment process but does not constitute development approval.
Goodman has planning consent for Project Apollo, a five-storey data centre at 4-10 Talavera Road. The AU$1.4 billion development has a planned capacity of 135MW and includes eight data halls, 66 backup generators and 36 cooling towers.
The proposed residential development is at 3-5 Talavera Road, while Project Apollo occupies 4–10 Talavera Road. The proximity of the two proposals has raised questions about how operational noise from the data centre, including its cooling plant and backup generators, will be considered in the assessment of the residential development.
It is understood Project Apollo underwent a detailed acoustic assessment as part of its planning and approval process, including consideration of operational noise from cooling plant and backup generators.
The acoustic material for Project Apollo identifies a number of existing noise-sensitive receiver locations, including residential properties in the surrounding area and the North Ryde Early Learning Centre on Talavera Road. The proposed residential tower site at 3–5 Talavera Road is not separately identified among those locations.
As a result, how noise from the data centre may affect future residents will be a question for the assessment of the residential project.
It is understood that any acoustic assessment or mitigation measures required for the residential proposal will be considered as it progresses through the planning process and in accordance with relevant requirements. It is not clear whether Goodman intends to undertake additional assessment or mitigation beyond those requirements.
The residential proposal remains at an early stage. The two projects are separate proposals within Macquarie Park, Sydney’s established employment and mixed-use precinct where housing, transport, commercial development and digital infrastructure are increasingly being planned alongside one another.
The residential project’s assessment will provide a further test of how the planning system considers the interface between large-scale data centre infrastructure and new housing, particularly where cooling plant and backup generation are part of an approved facility.