Applied Digital completes 75 MW commissioning at Polaris Forge 2

Entrance to an Applied Digital facility | Image Courtesy: Applied Digital
November 25, 2026 at 10:02 PM GMT+8

Applied Digital, an artificial intelligence data center infrastructure company, has announced the completion of base-build commissioning for the first 75 MW of an initial 150 MW data center building at Polaris Forge 2 in Harwood, North Dakota.

In a press release the company said it has also completed the integrated fit-out of the first 25 MW data hall which has achieved Ready for Service on schedule. With the base-build infrastructure successfully tested and commissioned, the remaining 50 MW can now advance through fit-out and delivery. It is the company’s first Ready for Service milestone at its second AI Factory campus, following the delivery of 250 MW of operational critical IT load at Polaris Forge 1 in Ellendale, North Dakota.

“AI infrastructure demand is not theoretical for us. It’s backed by long-term customer commitments, and our focus is on delivering against them,” said Wes Cummins, Applied Digital Chairman and Chief Executive Officer. “With our second campus now reaching Ready for Service on schedule, we’re demonstrating that our execution model is repeatable. The ability to consistently turn contracted demand into delivered AI capacity is what will define the leaders in this industry, and that’s exactly what we’re doing at Applied Digital.”

The building is fully leased as part of a customer’s 200 MW long-term lease at Polaris Forge 2, contributing to Applied Digital’s portfolio of over US$ 41 billion in contracted base-term lease revenue.

Each 150 MW building at the Polaris Forge 2 AI Factory campus is commissioned in two 75 MW phases with three 25 MW data halls tested and commissioned in each phase.

Earlier this week Applied Digital announced it had entered into a new 18-year lease agreement with a tier-one investment-grade hyperscaler for 150 MW of critical IT capacity, providing around US$ 5.4 billion in base-term contracted revenue. The company expects to begin delivering that capacity in the first half of 2028, subject to applicable development milestones, utility arrangements, and regulatory approvals.